Valmet supplies automation to HSY’s new treatment plant

Valmet will supply automation and solids measurements to Helsinki Region Environmental Services Authority HSY’s new wastewater treatment plant, which is under construction in Espoo’s Blominmäki bedrock in Finland.

The order was placed by Are, the main technical building contractor of the project. The main project contractor is YIT. The order was included in Valmet’s Q1 2019 orders received. The value of the order is not disclosed. Delivery will take place in 2020 2021 and commissioning in 2021 2022.

HSY’s Viikinmäki bedrock treatment plant has been running with Valmet’s automation system since the 1990s. Its Valmet DNA automation system has been updated, and in the future, it will be possible to control the operations of the new Blominmäki bedrock treatment plant from the Viikinmäki control room.

Previous articleCapstone secures order for two C600 microturbines
Next articleISSF declares winners of Safety & Sustainability Awards
Stainless Steel World Publisher
Stainless Steel World is part of The KCI Media Group, a group of companies focused on building and sustaining global communities in the flow control industries. We publish news on a daily basis and connect business-to-business professionals through our online communities, publications, conferences and exhibitions.