ANTAM starts commissioning parts of P3FP

PT ANTAM announced the commissioning of the jetty, belt conveyor and refining facilities, which are part of the Pomalaa Ferronickel Plant Expansion Project (P3FP). As of the end of August 2014, the overall engineering, procurement and construction (EPC) progress of the P3FP reached 68%.

ANTAM’s new jetty facilities are expected to provide faster and more efficient nickel ore unloading process for use in ferronickel smelters. The new jetty has a capacity of 12,000DWT with unloading rate 2×500 ton per hour, faster from previous rate that utilised backhoe loaders.

Photo courtesy of ANTAM

The development of the 4km-long belt conveyor facilities are aimed to replace dump trucks which are currently used to transport nickel ore and coal from the jetty to the ferronickel plant. ANTAM also aims to augment the occupational safety aspect of nickel ore and coal transportation with the use of the belt conveyor.

Meanwhile, the new refining facility will increase the number of ANTAM’s refining facilities from one to two. With the addition, ANTAM expects more flexible refining operations at the Pomalaa ferronickel plants as the plant’s capacity increases. These commissioning imply the completion of work packages 1, 2 and 3 out of the 8 work packages for P3FP.

Previous articleAllied Alloys acquires Blue Alloys
Next articleMartifer Solar adds 90MW to Italian O&M portfolio
Stainless Steel World Publisher
Stainless Steel World is part of The KCI Media Group, a group of companies focused on building and sustaining global communities in the flow control industries. We publish news on a daily basis and connect business-to-business professionals through our online communities, publications, conferences and exhibitions.