Steel Dynamics, Inc. has recently awarded the contract for an expansion at its Roanoke Bar Division, located in Roanoke, Virginia to SMS group. The upgrade is to integrate a new reheating furnace and a new finishing area into the facility. With this USD 28M investment, the Roanoke Bar Division plans to utilize its existing excess melting and casting capability to increase rolling capacity from the current 500,000 tons to over 600,000 tons per year.
The supply package comprises a pusher-type high capacity reheating furnace designed to process 140 tons of billets per hour. The plan is to roll the billets into light sections and reinforcing bars from sizes #4 to #11, as well as corresponding round bars. The objective of the new reheating furnace is to increase productivity and improve energy efficiency, with the adoption of a smart combustion management system.
After the upgrade, the Roanoke Bar Division expects to increase production of rebar to over 200,000 tons per year. Commissioning is expected to commence at the end of 2017.